At the moment we are not focusing development efforts into Tasks as this is a legacy planning product that will be replaced by the new planning tools of Timeline, Activities and Boards.

This means that we will not introduce any new functionality into Tasks.

Best regards,
Karolina

Comments (3)

Karolina Jackson-Ward
Karolina Jackson-Ward

Karolina Jackson-Ward

Level
0
Score
41
Team

Hi Patrice,

Thanks for taking the time to give us some more feedback. We've had some similar feedback http://ideas.projectplace.com/feedbacks/207733-ressource-..., it would be nice if you want to go in and cast your vote there as well:)

Best regards,
Karolina

Hi!

The dependencies will continue to be displayed only graphically in Tasks. We are looking into some new planning tools that will incorporate this idea.

Our next planning horizon to tackle is look-ahead planning. This horizon is somewhere between action (the next couple of weeks) and master (the whole project). In this horizon dependencies - logical connections between start and end dates - could be a possibility.

Dear all,

At the moment we are not focusing development efforts into Tasks as this is a legacy planning product that will be replaced by the new planning tools of Timeline, Activities and Boards.

This means that we will not introduce any new functionality into Tasks.