Comments (3)

Yes, this should be addressed. Causes inconsistencies for reporting and goes against project management principles for being able to close off an activity that is actually not really "done"

Hi Stine and Robert, we have discussed this a bit internally and are suggesting to display a warning message if someone tries to set an activity to Done where there are still cards open. This way we can prevent people from accidentally closing activities where cards are not done at the same time as we allow flexibility when there is an active decision to close an activity before it is fully completed. How do you feel about this suggestion?

In some cases Cards priority can be demoted and it is not completed or moved to Done Status on the Board although we want to signal that the Plan Activity is Done. I don't recommend preventing Plan Activity from being promoted to Done because all associated Cards have not been promoted to Board Done Status.

DIMELO - SocialCRM software editor