Ylva Espling
Ylva Espling

Ylva Espling

Level
0
Score
0
Team

This is not in our current roadmap but something we have talked about implementing.

Comments (3)

Ylva Espling
Ylva Espling

Ylva Espling

Level
0
Score
0
Team

Hi Frank,
Thanks for your feedback! This is something that we understand could be quite useful and something we want to do. However we have not been able to prioritize this. It will be interesting to follow the interest for this idea!

Regards
Ylva

Ylva Espling
Ylva Espling

Ylva Espling

Level
0
Score
0
Team

This is not in our current roadmap but something we have talked about implementing.

Cathy Lewis
Cathy Lewis

Cathy Lewis

Level
0
Score
5

As a Project Manager I'm constantly trying to shorten lead times, but that does not work in current version. Successors not changing date if I shorten the lead time in the predecessor. The successor will only change date if I increase the lead time.
This makes the plan very time consuming to use.

DIMELO - social media platform editor